Project for the web limits and boundaries

Hello,

In this bolg I’m gonna write about “Project for the web limits and boundaries” as of now.

There are some important limitations that we should know if we are using Project for the web. These limits apply to both  projects and tasks.

Project limitations
FIELD  LIMIT
Maximum total tasks for a project 500
Maximum total duration for a project 3650 days (10 years)
Maximum total resources for a project 150
Maximum total links (successor only) for a project 600
Task limitations
FIELD  LIMIT
Maximum hierarchy level 10 levels
Maximum links (successor + predecessor) 20
Maximum duration of leaf task 1250 days
Maximum duration of a summary task 3650 days (10 years)
Maximum resources assigned to a task 20 resources
Supported date range for a task 1/1/1984 – 12/31/2149