Project for the web limits and boundaries
Hello,
In this bolg I’m gonna write about “Project for the web limits and boundaries” as of now.
There are some important limitations that we should know if we are using Project for the web. These limits apply to both projects and tasks.
Project limitations | |
FIELD | LIMIT |
Maximum total tasks for a project | 500 |
Maximum total duration for a project | 3650 days (10 years) |
Maximum total resources for a project | 150 |
Maximum total links (successor only) for a project | 600 |
Task limitations | |
FIELD | LIMIT |
Maximum hierarchy level | 10 levels |
Maximum links (successor + predecessor) | 20 |
Maximum duration of leaf task | 1250 days |
Maximum duration of a summary task | 3650 days (10 years) |
Maximum resources assigned to a task | 20 resources |
Supported date range for a task | 1/1/1984 – 12/31/2149 |